Oracle's Wisconsin AI datacenter may miss its 2027 deadline as power approval stalls

Power approval set to delay Oracle's Wisconsin AI datacenter

Oracle's Wisconsin AI datacenter may miss its 2027 deadline as power approval stalls

Oracle's Project Lighthouse in Port Washington, Wisconsin, could slip past its planned 2027 customer delivery because the transmission line needed to power it is still awaiting approval from the Public Service Commission of Wisconsin. Aterio's base case puts partial power in December 2027 and full supply in October 2028, and even that leaves little time for testing and commissioning. Oracle, which reportedly sent a force majeure notice on its New Mexico campus, says the project remains on schedule.

The problem is power. The campus cannot run until ATC connects it to the grid, and ATC cannot start building until the PSC approves its application.
  1. bunderbunder

    I don’t think they can weather delays like this. I have family in Port Washington and visit there often. From what I’ve seen public opposition to this project is intense and growing. Every day this project is delayed is another day for local officials to find new ways to hinder it.

  2. JSR_FDED

    It must be disconcerting to be an Oracle customer right now - knowing your license fees are not going to lead to improved products or better support. Instead they’re financing some rickety datacenter building scheme.

  3. bpodgursky

    Feels like Oracle outsourced all their datacenter construction to organizations that were not nimble enough to line up contingency plans for alternative power sources and expected grid connections to happen "like normal".

    Meta, OpenAI, Anthropic, SpaceX even Google have been more hands-on and haven't seen these power issues plaguing Oracle, probably because they have an actual internal A-teams on it, not lethargic contractors.